Here are 30 questions on FCFS(FIRST COME FIRST SERVED) process scheduling algorithms, .Each question is presented in a table format, followed by the solution with Gantt charts, average turnaround time (TAT), and average waiting time (WT).
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 3 |
P2 | 2 | 6 |
P3 | 4 | 4 |
P4 | 6 | 5 |
P5 | 8 | 2 |
P6 | 9 | 7 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 3 | 3 | 3 | 0 |
P2 | 2 | 6 | 9 | 7 | 1 |
P3 | 4 | 4 | 13 | 9 | 5 |
P4 | 6 | 5 | 18 | 12 | 7 |
P5 | 8 | 2 | 20 | 12 | 10 |
P6 | 9 | 7 | 27 | 18 | 11 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (3 + 7 + 9 + 12 + 12 + 18) / 6 = 61 / 6 = 10.17
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 1 + 5 + 7 + 10 + 11) / 6 = 34 / 6 = 5.67
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 5 |
P2 | 1 | 9 |
P3 | 2 | 6 |
P4 | 3 | 7 |
P5 | 5 | 4 |
P6 | 6 | 3 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 5 | 5 | 5 | 0 |
P2 | 1 | 9 | 14 | 13 | 4 |
P3 | 2 | 6 | 20 | 18 | 12 |
P4 | 3 | 7 | 27 | 24 | 17 |
P5 | 5 | 4 | 31 | 26 | 22 |
P6 | 6 | 3 | 34 | 28 | 25 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (5 + 13 + 18 + 24 + 26 + 28) / 6 = 114 / 6 = 19.00
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 4 + 12 + 17 + 22 + 25) / 6 = 80 / 6 = 13.33
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 2 |
P2 | 1 | 4 |
P3 | 2 | 8 |
P4 | 3 | 3 |
P5 | 4 | 7 |
P6 | 5 | 6 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 2 | 2 | 2 | 0 |
P2 | 1 | 4 | 6 | 5 | 1 |
P3 | 2 | 8 | 14 | 12 | 4 |
P4 | 3 | 3 | 17 | 14 | 11 |
P5 | 4 | 7 | 24 | 20 | 13 |
P6 | 5 | 6 | 30 | 25 | 19 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (2 + 5 + 12 + 14 + 20 + 25) / 6 = 78 / 6 = 13.00
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 1 + 4 + 11 + 13 + 19) / 6 = 48 / 6 = 8.00
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 6 |
P2 | 1 | 3 |
P3 | 2 | 5 |
P4 | 3 | 7 |
P5 | 5 | 4 |
P6 | 6 | 2 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 6 | 6 | 6 | 0 |
P2 | 1 | 3 | 9 | 8 | 5 |
P3 | 2 | 5 | 14 | 12 | 7 |
P4 | 3 | 7 | 21 | 18 | 11 |
P5 | 5 | 4 | 25 | 20 | 16 |
P6 | 6 | 2 | 27 | 21 | 19 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (6 + 8 + 12 + 18 + 20 + 21) / 6 = 85 / 6 = 14.17
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 5 + 7 + 11 + 16 + 19) / 6 = 58 / 6 = 9.67
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 7 |
P2 | 2 | 2 |
P3 | 4 | 6 |
P4 | 6 | 5 |
P5 | 8 | 3 |
P6 | 10 | 8 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 7 | 7 | 7 | 0 |
P2 | 2 | 2 | 9 | 7 | 5 |
P3 | 4 | 6 | 15 | 11 | 5 |
P4 | 6 | 5 | 20 | 14 | 9 |
P5 | 8 | 3 | 23 | 15 | 12 |
P6 | 10 | 8 | 31 | 21 | 13 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (7 + 7 + 11 + 14 + 15 + 21) / 6 = 75 / 6 = 12.50
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 5 + 5 + 9 + 12 + 13) / 6 = 44 / 6 = 7.33
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 1 | 4 |
P2 | 2 | 5 |
P3 | 3 | 6 |
P4 | 4 | 7 |
P5 | 5 | 8 |
P6 | 6 | 9 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 1 | 4 | 5 | 4 | 0 |
P2 | 2 | 5 | 10 | 8 | 3 |
P3 | 3 | 6 | 16 | 13 | 7 |
P4 | 4 | 7 | 23 | 19 | 12 |
P5 | 5 | 8 | 31 | 26 | 18 |
P6 | 6 | 9 | 40 | 34 | 25 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (4 + 8 + 13 + 19 + 26 + 34) / 6 = 104 / 6 = 17.33
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 3 + 7 + 12 + 18 + 25) / 6 = 65 / 6 = 10.83
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 4 |
P2 | 1 | 6 |
P3 | 2 | 8 |
P4 | 3 | 3 |
P5 | 4 | 5 |
P6 | 5 | 2 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 4 | 4 | 4 | 0 |
P2 | 1 | 6 | 10 | 9 | 3 |
P3 | 2 | 8 | 18 | 16 | 8 |
P4 | 3 | 3 | 21 | 18 | 15 |
P5 | 4 | 5 | 26 | 22 | 17 |
P6 | 5 | 2 | 28 | 23 | 21 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (4 + 9 + 16 + 18 + 22 + 23) / 6 = 92 / 6 = 15.33
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 3 + 8 + 15 + 17 + 21) / 6 = 64 / 6 = 10.67
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 4 |
P2 | 1 | 5 |
P3 | 2 | 6 |
P4 | 3 | 7 |
P5 | 4 | 8 |
P6 | 5 | 9 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 4 | 4 | 4 | 0 |
P2 | 1 | 5 | 9 | 8 | 3 |
P3 | 2 | 6 | 15 | 13 | 7 |
P4 | 3 | 7 | 22 | 19 | 12 |
P5 | 4 | 8 | 30 | 26 | 18 |
P6 | 5 | 9 | 39 | 34 | 25 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (4 + 8 + 13 + 19 + 26 + 34) / 6 = 104 / 6 = 17.33
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 3 + 7 + 12 + 18 + 25) / 6 = 65 / 6 = 10.83
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 3 |
P2 | 1 | 4 |
P3 | 2 | 5 |
P4 | 3 | 6 |
P5 | 4 | 7 |
P6 | 5 | 8 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 3 | 3 | 3 | 0 |
P2 | 1 | 4 | 7 | 6 | 2 |
P3 | 2 | 5 | 12 | 10 | 5 |
P4 | 3 | 6 | 18 | 15 | 9 |
P5 | 4 | 7 | 25 | 21 | 14 |
P6 | 5 | 8 | 33 | 28 | 20 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (3 + 6 + 10 + 15 + 21 + 28) / 6 = 83 / 6 = 13.83
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 2 + 5 + 9 + 14 + 20) / 6 = 50 / 6 = 8.33
find the average Turn Around Time and Waiting Time of following processes using FCFS(FIRST COME FIRST SERVED) process scheduling algorithm?
Process | Arrival Time (AT) | Burst Time (BT) |
---|---|---|
P1 | 0 | 4 |
P2 | 1 | 5 |
P3 | 2 | 6 |
P4 | 3 | 7 |
P5 | 4 | 8 |
P6 | 5 | 9 |
Formulas :
Turn Around Time (TAT) = Completion Time (CT) - Arrival Time (AT)
Waiting Time (WT) = Turn Around Time (TAT) - Burst Time (BT)
Process | Arrival Time (AT) | Burst Time (BT) | Completion Time (CT) | Turn Around Time (TAT) | Waiting Time (WT) |
---|---|---|---|---|---|
P1 | 0 | 4 | 4 | 4 | 0 |
P2 | 1 | 5 | 9 | 8 | 3 |
P3 | 2 | 6 | 15 | 13 | 7 |
P4 | 3 | 7 | 22 | 19 | 12 |
P5 | 4 | 8 | 30 | 26 | 18 |
P6 | 5 | 9 | 39 | 34 | 25 |
Formulas:
Average Turn Around Time (TAT) = (TAT1 + TAT2 + TAT3 + TAT4 + TAT5 + TAT6) / 6 = (4 + 8 + 13 + 19 + 26 + 34) / 6 = 104 / 6 = 17.33
Average Waiting Time (WT) = (WT1 + WT2 + WT3 + WT4 + WT5 + WT6) / 6 = (0 + 3 + 7 + 12 + 18 + 25) / 6 = 65 / 6 = 10.83